Friday 7 November 2014

Early Years Hub - Week 25

The Sedum planted roof was installed this week

Work on the adjacent Campus Square

Progress inside the Early Years' Hub
Activity/Observations
Latest Progress on the EYH:

 Roof sedum, ballast and margins
 Roof outlets and rain water down pipes
 Window/door/curtain walling installations advanced
 Internal MF partitions + boarding + skim
 Air tightness membrane, final stages
 Laytex floors, commencing west of building
 Electrical 2nd fix
 Mechanical 2nd fix
 External cape-cod cladding
 Retainer block walls, paving, steps ramps, etc., west of building/campus square + Continuation of block work retaining walls