The Sedum planted roof was installed this week |
Work on the adjacent Campus Square |
Progress inside the Early Years' Hub |
Latest Progress on the EYH:
Roof sedum, ballast and margins
Roof outlets and rain water down pipes
Window/door/curtain walling installations advanced
Internal MF partitions + boarding + skim
Air tightness membrane, final stages
Laytex floors, commencing west of building
Electrical 2nd fix
Mechanical 2nd fix
External cape-cod cladding
Retainer block walls, paving, steps ramps, etc., west of building/campus square + Continuation of block work retaining walls