Monday 20 October 2014

Early Years Hub - Week 22

Activity/Observations Roof insulation and single ply to completion
 Window/door/curtain walling installations advanced
 Internal MF partitions + boarding
 Electrical containment + 1st fix
 Mechanical 1st and 2nd fix
 Air tightness membrane + tape, include lining insulation to completion
 External boarding cross battening ahead of cladding
 Levels reduced to west of building/campus square


Progress on the exterior facing Campus Square

Progress on the internal partitions

Pipework and equipment being installed in the plant room


Battens to the exterior being prepared to receive the cladding