Mechanical & Electrical works are continuing.First light fittings installed and working.
Finishes to wall boarding and ceilings are continuing.
Acoustic separating floor system repairs and replacing of areas to complete.
Fitting of vertical slabs to the perimeter of the floor slab is now continuing.
Single ply roof covering and flashings almost complete.
Fitting of cedar fascias, barge boards and window cheeks are almost complete.
Decorations are in progress.
Metal framed bulkheads, ceilings and suspended ceiling grids being erected.
Wall tiling is continuing, including tiling to hydro pool.
Soila and vent pipes and sink waste pipes being fitted and testing started.
Plumbing panels are continuing.
Works within Atrium is in progress.
Gutter fixing is to complete.
2nd fix Carpentry is continuing.
Storm water drainage connections from down pipe positions continuing.
Decking to enclosed external terraced areas to complete.
Foundations to retaining walls in place and brickwork started.
Laying of vinyl floor covering is progressing to various areas.
Furniture fitting is continuing.
General external works started.
Lift installation to both areas in progress.
So what's next?
Continue external works, vertical slabs to floor slab, roof covering flashings, internal wall boarding, decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, furniture fitting.
Progress in the Hydrotherapy Pool |
Fixed furniture installation in KS3 Classroom |
Sixth Form corridor |
Sprung floor installation in the School Hall |
Primary outdoor area - kerbs and edges being installed |
Work on the secondary hard play area |
Paths and edges to the secondary side |
No comments:
Post a Comment