Monday 17 November 2014

Wyre Forest School- Week 71

Activity/Observation
 Mechanical & Electrical works are continuing.First light fittings installed and working.
 Finishes to wall boarding and ceilings are continuing.
 Acoustic separating floor system repairs and replacing of areas to complete.
 Fitting of vertical slabs to the perimeter of the floor slab is now continuing.
 Single ply roof covering and flashings almost complete.
 Fitting of cedar fascias, barge boards and window cheeks are almost complete.
 Decorations are in progress.
 Metal framed bulkheads, ceilings and suspended ceiling grids being erected.
 Wall tiling is continuing, including tiling to hydro pool.
 Soila and vent pipes and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 Gutter fixing is to complete.
 2nd fix Carpentry is continuing.
 Storm water drainage connections from down pipe positions continuing.
 Decking to enclosed external terraced areas to complete.
 Foundations to retaining walls in place and brickwork started.
 Laying of vinyl floor covering is progressing to various areas.
 Furniture fitting is continuing.
 General external works started.
 Lift installation to both areas in progress.

So what's next?
 Continue external works, vertical slabs to floor slab, roof covering flashings, internal wall boarding, decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, furniture fitting.

Progress in the Hydrotherapy Pool

Fixed furniture installation in KS3 Classroom

Sixth Form corridor

Sprung floor installation in the School Hall

Primary outdoor area - kerbs and edges being installed


Work on the secondary hard play area


Paths and edges to the secondary side