Friday 7 November 2014

Wyre Forest School - Week 61

Key Stage 3/4 areas emerge

Gas supply entering the building

Rendering of the hydrotherapy pool prior to tiling

Plumbed panelling to Bathroom Management Areas


Progress on the Sports Hall Ceiling with perforated boards, recesses created for lighting.
 Activity/Observation
 Fitting of bitroc sheathing board is almost complete to external walls.
 Blown cavity insulation is complete.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are continuing.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is continuing.
 1st coat wall decorations are being carried out as areas become available.
 Metal framed bulkheads and ceilings being constructed.
 Soil and vent pipes and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 Floor screed to falls in wet areas are laid.
 External scaffold is being dismantled as required.
 Gutter fixing started.

So what's next?
 Continue scaffold erection, fitting of bit roc, window fitting and battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, soil and vent pipes