Monday 10 November 2014

Wyre Forest School - Week 70

Activity/Observation
 M & E works are continuing.
 Finishes to wall boarding and ceilings are continuing.
 Acoustic separating floor system repairs and replacing of areas to complete.
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is progressing, flashings to complete.
 Fitting of cedar fascia's, barge boards and window cheeks are almost complete.
 Decorations are in progress.
 M.F. bulkheads, ceilings and suspended ceiling grids being erected.
 Wall tiling is continuing, including tiling to hydro pool.
 S.V.P.s and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 Gutter fixing is to complete.
 2nd fix Carpentry is continuing.
 Storm water drainage connections from down pipe positions continuing.
 Decking to enclosed external terraced areas to complete, green roof area laid.
 Foundations to retaining walls in place and brickwork started.
 Laying of vinyl floor covering is progressing.
 Furniture fitting has started.
 General external works started.
 Lift installation in progress.

So what's next?
 Continue external works, vertical slabs to floor slab, roof covering flashings, internal wall boarding, decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, furniture fitting.
Retaining walls in Camous Square being built

Retaining wall to Primary hard play

External works kerbs etc underway to secondary age outdoor areas

Roof terrace with sedum area and decking

Preparing a lift shaft with chains and rails for teh lft car instalation

Main Foyer - the main stair is installed

The sides of the pool are now tiled with mosaic

Classroom with practical area waiting for sink unit to be installed

Staff room with kitchenette units installed.