Monday 17 November 2014

Early Years Hub - week 26

Progress this week:

Activity/Observations
 Remove all scaffold
 Internal Metal Framed partitions + boarding + skim
 Air tightness membrane, final stages
 Latex floors, commencing west of building
 Electrical 2nd fix
 Mechanical 2nd fix, fan coil heaters, etc.
 Plumber 1st fix
 Carpentry 2nd fix
 Retainer block walls, paving, steps ramps, etc. west of building/campus square + Continuation of block work retaining walls – Further excavations and concrete foundations, retainers to N/W of building
 Further drainage around the building
Ramp being formed on Campus Square

Early Years Hub - Year 1 classes

Cisterns and pipework ready to be concealed in panelling


Reception Classroom

Reception Classroom