Activity/Observations
Roof tiling, later stages and proprietary flashing to Velux roof windows
Fermacell fire lining and plaster boarding continues to 1st and 2nd floors
Electrical 1st fix, includes containment, baskets, etc
Sprinkler installations up to 1st Fix
Acoustic in-fill work to service suspension bars
Commence carpentry 1st fix, doors and linings to 1st floor circulation
Mechanical 1st fix /plumbing + air ducting + boilers installed
Cedar cladding, weather boarding + support framing – now around 50% complete
Limited ground works - mainly services in and around
The velux rooflight with its proprietary flashing prior to roof tiling |
The garden being laid out with channels and edgings |
Battens on the facade prior to timber cladding |
The first floor bedroom corridor |