Monday 17 February 2014

Weekly Boarding Week 32

Cable trays and pipework installed above ceilings

Kerbs being laid out for the parking and entrance from Moule Close

The facade is being prepared for rendering

The garden is being laid out with sett channels
Activity/Observations
 Roof tiling, later stages and proprietary flashing to Velux
 Fermacell fire lining and plaster boarding continues to 1st and 2nd floors, includes taping/jointing
 Electrical 1st fix cable installations includes containment, baskets, etc
 Sprinkler installations up to 1st Fix
 Fix render carrier panels ahead of rendering
 Mechanical 1st fix /plumbing + air ducting + boilers installed
 Cedar cladding, weather boarding + support framing – now around 90% complete
 Limited ground works - mainly setts to channels and paved terrace