Monday 17 February 2014

Science Block - Week 32


All the windows are now fitted to Science Block

Brackets fitted to take external sun shading to the south facing windows

Battening and insulation to the acoustic floor
This week...

Activity/Observations

 Fitting of airtightness tapes is almost complete.
 Scaffold erection is continuing as required, internal and external.
 Fitting of insulation, sound block plaster board and taping is almost complete to ground floor ceiling areas.
 Fitting of window frames is complete.
 Fermacell boarding to ground floor walls are continuing and filling has started.
 Acoustic insulation to internal walls is advanced.
 Sprinkler pipe work is almost complete.
 Mechanical 1st fix including ducting is continuing.
 Electrical 1st fix containment is continuing.
 Perimeter D.P.M. repaired and vertical slabs fitted.
 Single ply roofing has started to upper roof area.
 Acoustic flooring has started to first floor classroom areas.


So what's next?
 Complete sarket board, scaffold erection, continue boarding ceilings, continue ducting, and mechanical pipe work, 1st fix electrics, fermacell boarding to internal walls, single ply roof coverings.