Progress on the Sports Hall

Ceiling and timber beams above the atrium being prepared for painting

Progress on a first floor classroom

The 6th form external terrace

Progress on a classroom in the East Wing
Activity/Observation
 Mechanical & Electrical works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screedboard floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are almost complete.
 Fitting of cedar fascias and barge boards are almost complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is continuing.
 1st coat wall decorations are being carried out as areas become available.
 Mrtal framed bulkheads and ceilings being constructed.
 Suspended ceiling grids have started.
 Wall tiling about to start.
 Soil and vent pipes and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 External scaffold is being dismantled as required.
 Gutter fixing started.
So what's next?
 Continue scaffold dismantle, vertical slabs to floor slab, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, Soil and vent pipes.