Activity/Observation
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc board is almost complete to external walls.
 Blown cavity insulation is continuing to walls and roof voids as areas become available.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are continuing.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is continuing.
 1st coat wall decorations are being carried out as areas become available.
 Bulkheads and ceilings being constructed.
 S.V.P.s and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 Floor screed to falls in wet areas being laid.
 External scaffold is being dismantled as required.

So what's next?
 Continue scaffold erection, fitting of bitroc, window fitting and battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, Soil and vent pipes.

Campus square elevation with the scaffold removed

Progress on the Sports Hall


Scaffolding has been removed from the Keystage 3/4 wing

Work on the Sports Hall ceiling from a scaffold platform

The first floor walkway around the atrium

Floor screed being laid to falls in the pool changing areas

No comments:

Post a Comment