M & E works are in progress, including fitting of sprinkler system.
Internal boarding to walls and ceilings are continuing.
Acoustic separating floor system continuing (screed board floors to complete as areas become available).
Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
Single ply roof covering is continuing and flashings to complete.
Fitting of air tightness membranes are almost complete.
Fitting of cedar fascias and barge boards are almost complete.
Cape Cod cladding is continuing.
Fitting of render boards and rendering is continuing.
1st coat wall decorations are being carried out as areas become available.
M.F. bulkheads and ceilings being constructed.
Suspended ceiling grids have started.
Wall tiling about to start.
Soil pipes and sink waste pipes being fitted and testing started.
Plumbing panels are continuing.
Works within Atrium is in progress.
External scaffold is being dismantled as required.
Gutter fixing started.
So what's next?
Continue scaffold dismantle, vertical slabs to floor slab, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings.
The ceiling over the Atrium is almost complete |
There are two large rooflights over the Foyer |
Progress on a classroom in the east wing |
Curtain walling glazing has been added to the main entrance |
The primary wing |