Tuesday 23 September 2014

Wyre Forest School - week 63

Activity/Observation
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are almost complete.
 Fitting of cedar fascias and barge boards are almost complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is continuing.
 1st coat wall decorations are being carried out as areas become available.
 M.F. bulkheads and ceilings being constructed.
 Suspended ceiling grids have started.
 Wall tiling about to start.
 Soil pipes and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 External scaffold is being dismantled as required.
 Gutter fixing started.

So what's next?
 Continue scaffold dismantle, vertical slabs to floor slab, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings.

The ceiling over the Atrium is almost complete

There are two large rooflights over the Foyer

Progress on a classroom in the east wing

Curtain walling glazing has been added to the main entrance

The primary wing

No comments:

Post a Comment