Monday 9 September 2013

What's happening on site? - week 9

Wyre Forest School:
 Continue installing below ground drainage
 Reduced levels completed
 Form retaining wall base, set up formwork/steel reinforcement, insulation, DPM membrane, etc to south of school.

Artificial Grass Sports pitch
 Excavated structural fill removed to the to the all weather pitch to make up levels.
 Landscape fill to ongoing terrace landscape area mainly to south and west.


Weekly Boarding Unit
Construction of Substructure to slab
 Excavate for below slab drainage runs and sprinkler supply
 Install below slab drainage runs – concrete bed + surround
 Sprinkler supply installed
 Gabion foundations in for sprinkler tank and pump house

Science Block
 Excavations for foundations, include timber formwork to contain top of pour
 Vertical insulation to foundation edge positioned prior and during pour
 Commence below slab foul drains, ahead of localised concrete foundation pours