Tuesday 27 August 2013

Works on Site: Week 6

Progress on site this week:

Wyre Forest School:

 Bulk excavations to reduced level are almost complete.
 Below ground drainage begins to be laid
 Reduce levels continuing to formation/excavations to form retaining wall base, south of school.
 Structural fill excavated from retaining wall is being taken to the artificial grass pitch to make up levels.
 Landscape fill is ongoing terrace landscape area.

Weekly Boarding Unit

 Setting out and excavations for gabion cage foundation to Sprinkler Tank area has commenced.
 Foul drainage outdside of the foot print of the building is now in place.
 Building of drainage manholes has begun.

Science Block

 Structural fill is now complete.
 Sub base stone cap layer laid levelled and compacted to underside of floor slab make up.
 Reduce dig to rear paved area is in progress.

Manhole template being laid out for Weekly Boarding Unit


Structural fill being laid for the Science Block
 