Monday 23 September 2013

Progress on site - Week 11


Wyre Forest School

 Continuing to lay below ground drainage.
 Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
 Steel reinforcing fixing to retaining wall of south wing is in progress.
 Shuttering, damp proof membrane. is in progress to east wing.
 Excavation to hydrotherapy pool has been carried out and base is blinded with concrete.
 Excavations to lift pit and trampoline pit are almost complete.

Science Block

 Excavation and concreting of foundations, include timber formwork to contain top of pour is continuing approx 65% complete.
 Below slab foul drains continuing to be laid, ahead of localised concrete foundation pours and water test is in progress.


Weekly Boarding Unit

Complete stone regarding/compaction + sand blind ready for the ground floor slab
 Set up perimeter formwork
 Lay floor insulation and damp proof membrane
 Assemble steel fabric reinforcement ready to pour concrete