Monday 16 September 2013

What's happening on site? Week 10

Latest progress:

Science Block
 Excavation and concreting of foundations, include timber formwork to contain top of pour is continuing approx 40% complete.
 Below slab foul drains continuing, ahead of localised concrete foundation pours and water test is in progress.

Wyre Forest School
 Continue below ground drainage.
 Concreting of retaining wall / floor slab has started and preparation for floor slab pours is continuing.
 Excavation of soak away 2 is complete, granular base laid, geo textile wrap in place and placing of geo textile cellular units have started.

Weekly Boarding Unit
Substructure to slab
 Install below slab drainage runs to completion – concrete bed + surround – water tested
 All service ducts now installed
 Commence grading and blinding
 Gabion foundations in for sprinkler tank area





No comments:

Post a Comment