Science Block
Excavation and concreting of foundations, include timber formwork to contain top of pour is continuing approx 40% complete.
Below slab foul drains continuing, ahead of localised concrete foundation pours and water test is in progress.
Wyre Forest School
Continue below ground drainage.
Concreting of retaining wall / floor slab has started and preparation for floor slab pours is continuing.
Excavation of soak away 2 is complete, granular base laid, geo textile wrap in place and placing of geo textile cellular units have started.
Weekly Boarding Unit
Substructure to slab
Install below slab drainage runs to completion – concrete bed + surround – water tested
All service ducts now installed
Commence grading and blinding
Gabion foundations in for sprinkler tank area