Monday 23 February 2015

Wyre Forest School - week 85- close to internal completion

Activity/Observation
 M & E finishing items are continuing.
 Single ply roof covering flashings to complete.
 Fitting of cedar fascia's, barge boards and window cheeks are complete, remedial works to do.
 Decorations are continuing including snag items.
 Gutter fixing is to complete.
Carpentry finishing items are continuing including snag items.
 Laying of vinyl floor covering and carpets are continuing.
 General external works continuing, including tarmacing.
 Data installation progressing.
 Generally all trades are progressing towards practical completion.

Drop-off areas (top) and primary play (below)
Secondary Play and Campus Square
Pool hall, Main Foyer, Key Stage 1/2 
Key Stage 1/2
Atrium library, Key stage 3 areas
Key Stage 3 and Sports Hall
Key Stage 4 and Dining Hall
Main Hall and Sixth Form