Monday 16 February 2015

Wyre Forest School - Week 84

Activity/Observation
 M & E 2nd fix/ finishing items are continuing.
 Single ply roof covering flashings started this week.
 Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
 Decorations are continuing including snag items.
 Plumbing panels are fitted, basin and hinged rail fixings to address.
 Gutter fixing is to complete.
Carpentry finishing items are continuing including snag items.
 Face brickwork to retaining walls started again this week.
 Laying of vinyl floor covering and carpets are continuing.
 General external works continuing.
 Data installation progressing.
 Generally all trades are progressing towards practical completion.
 Filling of hydro pool carried out.

Tarmac laying for the minibus drop off area
Route to the Early Years by primary play
Campus Square link to Early Years
The hall set up with dining tables
Kay Stage 4 classroom
Key Stage 2 Classroom
Sensory Foyer
Key Stage 3 Classroom
Floor laying in the atrium
The pool is filled with water for the first time