Tuesday 8 July 2014

Wyre Forest Special School - Week 52

Activity/Observations
 Timber frame erection is continuing.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc board is continuing to external walls and blown cavity insulation is continuing as areas become available.
 M & E works are in progress.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Roof membrane and counter batten fixing is continuing.
 Roof tiling is continuing as areas become available.
 Single ply roof covering is continuing, flashings to complete.
 Fitting of air tightness membranes are continuing.
 Scaffold erection is continuing as required.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering started.
 1st coat wall decorations are in progress.
 Floor screeds to B.M.A.s, shower rooms and toilets in progress.

So what's next?
 Continue scaffold erection, timber frame erection, fitting of bit roc, window fitting and battening, roof membranes and counter battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, acoustic floor.



View from around the building

Progress on the roof- battens, underlay and tiling

View of the upper part of the atrium

Progress on the Foyer area