Tuesday 1 July 2014

Wyre Forest School - Week 51

Activity/Observations
 Timber frame erection is continuing.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc board is continuing to external walls and blown cavity insulation is continuing as areas become available.
 Mechanical & Electrical works are in progress.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Roof membrane and counter batten fixing is continuing.
 Roof tiling is continuing as areas become available.
 Single ply roof covering is continuing , flashings to complete.
 Fitting of air tightness membranes are continuing.
 Scaffold erection is continuing as required.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering started.

Programme*

So what's next?
 Continue scaffold erection, timber frame erection, fitting of bit roc, window fitting and battening, roof membranes and counter battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, acoustic floor.

Cantilevered corner of the staff room over the main entrance


Timber framing forms an 'arched' opening over the stage area of the hall

Gas and water supplies enter the building at basement level
Render carrier board and render to the hall elevation

Sixth form corridor as timber shell with temporary propping




The hall elevation to Campus Square

Interior of the school hall