Monday 14 July 2014

Wyre Forest School - Week 53

Activity/Observations
 Timber frame erection is continuing.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc board is continuing to external walls and blown cavity insulation is continuing as areas become available.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings is continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Roof tiling is continuing and is close to completion.
 Single ply roof covering is continuing, flashings to complete.
 Fitting of air tightness membranes is continuing.
 Scaffold erection is continuing as required.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering started.
 1st coat wall decorations are being carried out as areas become available.
 M.F. bulkheads and ceilings being constructed.

So what's next?
 Continue scaffold erection, timber frame erection, fitting of bit roc, window fitting and battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, mist coat decorations and acoustic floor.

Rendering of the first floor walls has begun

Breather membrane, tiling battens and roof tiling. The lighting conductor tape can be seen running up the roof.

The air handling plant room for the pool, awaiting equipment

The Sports hall, full of scaffolding to work on the walls and ceiling.


The dining hall, with sprinkler pipework being installed above the ceiling.