 Back fill and floor slab preparation is continuing to perimeter of hydro pool, including Water Play Room.
 Cutting, placing and fixing of soleplates for the timber framed walls are in progress.
 Erection of perimeter scaffold is continuing.
 Make up levels in 6f2 is almost complete to main car park area, curb laying, ducting and drainage continuing. Shaping up in type 1 material has started.

So what's next?
 Continue floor slab / cantilevered floor around hydro pool, scaffold erection, fixing of sole plates kerbs to car park and shape up with type 1.
The first deliveries of the timber frame panels are due shortly.

View of the school showing the lift shafts (as seen from the top of the Science Block)

Excavating for the Water Play Sensory Room alongside the pool


Surveying, levelling and laying kerbs for the Special School car park