Science Block: battening for external insulation layer |
View looking down onto the atrium at first floor level |
The first waterproofing layer being added to the roof, showing the clerestory window openings in the background. |
Activity/Observations
Timber frame erection is continuing. Roof cassette fitting is almost complete.
Fitting of air tightness tapes are continuing as areas become available.
Setting up and fitting of metal floor ducts for science lab services (gas, water, electricity) are almost complete.
Scaffold erection is continuing as required.
Fitting of torch on membrane to lower roof area has started.
So what's next?
Continue timber frame erection, fitting of air leakage tapes, scaffold erection, floor duct fitting, roof covering membrane, start boarding ceilings, start ducting.