Monday 7 October 2013

Progress on the Wyre Forest School - Week 12

 Continue below ground drainage, tests carried out on each drain run when complete..
 Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
 Steel reinforcing fixing to retaining wall of south wing is in progress.
 Concreting of floor slab to east wing is complete.
 Hydro pool construction is continuing.
 Excavations to lift pit and trampoline pit are complete, damp proof membrane and reinforcement steelwork is in place.
 Excavation for foul drainage at site boundary has started.
Overview of the busy site




No comments:

Post a Comment