Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
Steel reinforcing fixing to retaining wall of south wing is in progress.
Concreting of floor slab to east wing is complete. Hydro pool construction is continuing.
Excavations to lift pit and trampoline pit are complete, damp proof membrane and reinforcement steelwork is in place.
Excavation for foul drainage at site boundary has started.