Friday 26 July 2013

Works on site: week 3

What has been happening on site this week?

- Warm and dry weather - good progress.

Weekly Boarding: area prepared for pile rig

Wyre Forest School: haul road established, benning stripping turf from building footprint.

Science block: Site strip and reducing levels, grubbing out old concrete bases.

Generally: Preparing ground and foundation pads for site offices.