Friday 16 January 2015

Wyre Forest School -Week 80 (0verall contract week 94)

Progress this week:

  •  Mechanical & Electrical  2nd fix/ finishing items are continuing.
  •  Single ply roof covering flashings to complete.
  •  Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
  •  Decorations are continuing.
  •  Tiles to ceilings almost complete.
  •  Wall and floor tiling to hydro pool is continuing.
  •  Sanitary items being fitted.
  •  Plumbing panels are fitted, basin and hinged rail fixings to be completed.
  •  Gutter fixing is to complete.
  •  Carpentry finishing items are in progress.
  •  Face brickwork to retaining walls are almost complete.
  •  Laying of vinyl floor covering and carpets are in progress.
  •  Furniture fitting is to complete.
  •  General external works continuing.
  •  Erection of canopies and glazing started.
  •  Data installation progressing.
  •  Site offices have been vacated this week, services disconnected and removal from site expected Friday of this week.
The covered canopy around the main entrance is being erected

The base for the Key stage 1/2 games court

Work progressing on the Primary outdoor areas

Floor laying in the Foyer

KS3 Classroom, carpets laid and protection laid over

The movable partition between the hall and dining areas is installed

First Floor landing by the atrium