Monday 11 August 2014

Habberley Learning Campus– Wyre Forest Special School - Week 57

Progress around the main entrance and Sports Hall

Framework for the panelling concealing plumbing in toilet areas

One of the outdoor terraces


Ventilation ducts being installed in a first floor classroom
 Activity/Observations
 Timber frame erection is almost complete.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc sheathing board is almost complete to external walls.
 Blown cavity insulation is continuing to walls and roof voids as areas become available.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are continuing.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is in progress.
 1st coat wall decorations are being carried out as areas become available.
 Metal framed bulkheads and ceilings being constructed.
 S.V.P.s and sink waste pipes being fitted and testing started.
 Plumbing panels started.


No comments:

Post a Comment