Activity/Observation
M & E 2nd fix/ finishing items are continuing.
Single ply roof covering flashings to complete.
Fitting of cedar fascias, barge boards and window cheeks are complete.
Decorations are continuing.
Wall and floor tiling to hydro pool is almost complete.
Sanitary items being fitted.
Plumbing panels are fitted, basin and hinged rail fixings to address.
Gutter fixing is to complete.
Carpentry finishing items are in progress.
Face brickwork to retaining walls are almost complete.
Laying of vinyl floor covering and carpets are continuing.
Furniture fitting is to complete.
General external works continuing.
Erection of canopies and glazing well advanced.
Data installation progressing
The pavilion canopies (previously at Bewdley Road) have been installed at the new school. |
The front canopy has been installed |
Progress on the Primary outdoor areas |
The assembly hall as seen from the dining area |
Linoleum being laid around the atrium, level 1 |
Sixth form kitchenette |
Key Stage 4 classroom |