- Mechanical & Electrical 2nd fix/ finishing items are continuing.
- Single ply roof covering flashings to complete.
- Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
- Decorations are continuing.
- Tiles to ceilings almost complete.
- Wall and floor tiling to hydro pool is continuing.
- Sanitary items being fitted.
- Plumbing panels are fitted, basin and hinged rail fixings to be completed.
- Gutter fixing is to complete.
- Carpentry finishing items are in progress.
- Face brickwork to retaining walls are almost complete.
- Laying of vinyl floor covering and carpets are in progress.
- Furniture fitting is to complete.
- General external works continuing.
- Erection of canopies and glazing started.
- Data installation progressing.
- Site offices have been vacated this week, services disconnected and removal from site expected Friday of this week.
The covered canopy around the main entrance is being erected |
The base for the Key stage 1/2 games court |
Work progressing on the Primary outdoor areas |
Floor laying in the Foyer |
KS3 Classroom, carpets laid and protection laid over |
The movable partition between the hall and dining areas is installed |
First Floor landing by the atrium |