Levelling the area which will be the games courts (Key stage 1/2) |
Landscaped play areas by the Primary classrooms |
Secondary outdoor social areas and games court |
Progress on the Foyer |
The first carpets are laid in classrooms |
The fitting out of the catering kitchen is well advanced |
Key Stage 3 corridor |
Stair and lift up to the hall and dining rooms |
Activity/Observation
M & E 2nd fix/ finishing items are continuing.
Acoustic separating floor system repairs and replacing of areas to complete.
Single ply roof covering flashings to complete.
Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
Decorations are continuing.
Tiles to ceilings almost complete.
Wall and floor tiling to hydro pool is continuing.
Sanitary items being fitted.
Plumbing panels are fitted
Gutter fixing is to complete.
2nd fix Carpentry is continuing.
Face brickwork to retaining walls are almost complete.
Laying of vinyl floor covering and carpets are in progress.
Furniture fitting is to complete.
General external works continuing.