Activity/Observations
Continue erection of timber frame, envelope now complete - continue roof counter battens (70mm x 75mm) Install Tyvek breather membrane – Fit cedar fascia/barge – Parapets – roof tiles
Complete second skin sheathing and timber framing
Internal partition walls and floor zone 1st floor acoustic insulation + netting - commence floating/acoustic floor to 1st floor
Commence double layer fire line plaster boarding GF ceilings
Electrical first fix, containment
External door and window installations + taping etc
Warmcell installations, walls completed, roof to follow
Air tight membrane + taping now advanced
1st fix plumber soil and vent pipes for waste water
Kerb racing to parking and building approach, include line of swale (the swale is shallow ground depression designed to manage water runoff, filter pollutants, and increase rainwater infiltration)
So what's next?
Roof tiling, outer cladding
![]() |
Roof counterbattens being fixed-doubled up at the eaves and ridge, these allow overhangs to be formed without causing cold bridging, as unlike the roof casettes they lie ouside the insulation zone. |
![]() |
Roof with windtight breather membrane and battens on, with roof tiles laid out ready for fixing. |
![]() |
Inside the building with the plasterboard fixed to the floor soffit. |