Timber frame erection is continuing. Roof cassette fitting is continuing, clerestory frame fitting has started.
Air tightness tapes are being fitted.
Setting up of metal floor ducts is continuing.
Scaffold erection is continuing as required.
So what's next?
Continue timber frame erection, fitting of air leakage tapes, scaffold erection and floor duct fitting.
![]() |
The triangular central atrium and balcony |
Roof cassettes are being placed and the clerstorey walls erected |
Concrete floor slab primed and air tightness tapes being fitted. |