Final stage electrical 2nd fix, testing
Final stage internal carpentry to completion
Final stage Mechanical 2nd fix /plumbing, commissioning
Carpet tiles mostly complete to first floor. Carpet and rubber tac-tile flooring to ground floor
Final stage painting/decoration + Mural
Final stage ceilings lay-in tiles in-conjunction with services
Ground workers, shape up, tarmac base, kerbs, channels, swales, gullies, etc
Fencers return
Landscaping
Comments
Externals snagged Monday internals, Friday
| Within the enclosed garden, individual garden spaces are defined by low fences |
| The main kitchen is almost complete |
| Flat-packed furniture is being assembled |