Fermacell fire lining and plaster boarding now advanced - includes taping/jointing.
Continue electrical 1st fix & 2nd fix
Internal carpentry 2nd fix, doors (includes sliding doors + stud) and linings, stairs, kitchen units, cupboards, skirting, etc.
Mechanical 1st fix /plumbing
Decorations
Lift installations and commission
Ground works continue
Photos from this week
| The scaffolding has been removed. The blue and the yellow render panels denote the two 'houses' that the unit will be organised into. |
| View from the garden side. |
| The kitchen being installed |
| Ceilings have been installed in the corridor |