Activity/Observations
Timber frame erection is continuing to areas 1 and 2.
Service trench being excavated with laying of water main and ducts continuing.
Distribution of windows into rooms ready for fitting has started.
Fitting of bitroc sheathing board has started to external walls.
Programme*
Battening of walls, window fitting to start during next week.
So what's next?
Continue scaffold erection, timber frame erection, service trenches and ducts, fitting of bitroc,window fitting and battening.
![]() |
Looking across from the Sports Hall end of the building |
![]() |
Ground floor walls at the northern end - changing rooms by the Sports Hall |
![]() |
The first walls around the atrium |
![]() |
The curved walls being formed round the Foyer to the sensory rooms |