Monday, 18 May 2015

New Campus wins National Gold Award




Representatives of the Speller Metcalfe Malvern site team accept the Gold Award from Paul Everall, chief executive of Local Authority Building Control (centre)


Thw contractor responsible for the work creating the new Habberley Learning Campus, Speller Metcalfe, has won a prestigious Gold Award at the Considerate Constructors Scheme’s 2015 National Site Awards.

The new campus, in Habberley Road, Kidderminster, brings together two schools that specialise in learning difficulties and disabilities, to share a campus alongside Baxter College and St John's Primary School.

The annual awards, run by the scheme, recognise the highest levels of consideration and care shown by construction sites throughout the UK towards their local neighbourhood, the general public, their workforce and the environment. Only 98 UK sites achieved the gold standard this year from more than 9,000, making this site’s achievement particularly significant.

For the original article in the kidderminster Shuttle follow this link: http://www.kidderminstershuttle.co.uk/news/business_daily/12905700.Learning_difficulties_new_campus_win_national_gold_award/

Monday, 23 February 2015

Wyre Forest School - week 85- close to internal completion

Activity/Observation
 M & E finishing items are continuing.
 Single ply roof covering flashings to complete.
 Fitting of cedar fascia's, barge boards and window cheeks are complete, remedial works to do.
 Decorations are continuing including snag items.
 Gutter fixing is to complete.
Carpentry finishing items are continuing including snag items.
 Laying of vinyl floor covering and carpets are continuing.
 General external works continuing, including tarmacing.
 Data installation progressing.
 Generally all trades are progressing towards practical completion.

Drop-off areas (top) and primary play (below)
Secondary Play and Campus Square
Pool hall, Main Foyer, Key Stage 1/2 
Key Stage 1/2
Atrium library, Key stage 3 areas
Key Stage 3 and Sports Hall
Key Stage 4 and Dining Hall
Main Hall and Sixth Form

Monday, 16 February 2015

Wyre Forest School - Week 84

Activity/Observation
 M & E 2nd fix/ finishing items are continuing.
 Single ply roof covering flashings started this week.
 Fitting of cedar fascias, barge boards and window cheeks are complete, remedial works to do.
 Decorations are continuing including snag items.
 Plumbing panels are fitted, basin and hinged rail fixings to address.
 Gutter fixing is to complete.
Carpentry finishing items are continuing including snag items.
 Face brickwork to retaining walls started again this week.
 Laying of vinyl floor covering and carpets are continuing.
 General external works continuing.
 Data installation progressing.
 Generally all trades are progressing towards practical completion.
 Filling of hydro pool carried out.

Tarmac laying for the minibus drop off area
Route to the Early Years by primary play
Campus Square link to Early Years
The hall set up with dining tables
Kay Stage 4 classroom
Key Stage 2 Classroom
Sensory Foyer
Key Stage 3 Classroom
Floor laying in the atrium
The pool is filled with water for the first time

Friday, 6 February 2015

Wyre Forest School - week 83

Progress this week:

Activity/Observation

  • M & E 2nd fix/ finishing items are continuing.
  • Single ply roof covering flashings to complete.
  • Fitting of cedar fascia's, barge boards and window cheeks are complete, remedial works to do.
  •  Decorations are continuing.
  • Wall and floor tiling to hydro pool area is almost complete, filling of pool to now start next week.
  • Plumbing panels are fitted, basin and hinged rail fixings to address.
  •  Gutter fixing is to complete.
  • Carpentry finishing items are continuing.
  • Face brickwork to retaining walls are to complete.
  • Laying of vinyl floor covering and carpets are continuing.
  •  General external works continuing.
  •  Data installation progressing.
Canopy over the main entrance by the minibus drop off area

Primary hard court with ball-stop fencing

Key stage3/4 outdoor area with games court beyond, Baxter College in the distance

Sensory Foyer with stretch ceiling installed

Primary Food Tech Room

Sports Hall with line markings complete


Sixth Form Corridor


Vocational Hub Phase 1 Handover

The first phase of the Vocational Hub was handed over on Friday 30 January. This provides Food Technology/ Catering, Café, IT,  DT and Art facilities for the Wyre Forest School. The Vocational Hub is the refurbishment of a 1960s building on the Baxter College site, but now adjacent to the new (nearly complete) Wyre Forest School and fronting onto Campus Square.


The Café with beverage bar

The DT room looking onto Campus Square

The Food Tech/Catering room

The Food Tech/Catering room

Demonstration bench at the front of the Food Tech/Catering room

Height adjustable sink and hob in the Food Tech room

Demonstration bench

Combi oven in the Food Tech/Catering room


IT room

New accessible WC

New cleaners' store

Monday, 26 January 2015

Early Years Hub - Week 36


Activity/Observations 

 Carpets + protection

 Floor vinyl, now advanced and protected


 Electrical 2nd fix

  Mechanical 2nd fix, water heaters, etc.

  Plumber 2nd fix 

 Decorations

  Ceiling grids + lighting now advanced 

 Carpentry 2nd fix, 

 IPS, vanity units and proprietary cubicle partitions

 Canopy assembly




Wyre Forest School week 81

Progress this week:


Activity/Observation

 M & E 2nd fix/ finishing items are continuing.

 Single ply roof covering flashings to complete.

 Fitting of cedar fascias, barge boards and window cheeks are complete.

 Decorations are continuing.

 Wall and floor tiling to hydro pool is almost complete.

 Sanitary items being fitted.

 Plumbing panels are fitted, basin and hinged rail fixings to address.


 Gutter fixing is to complete.

Carpentry finishing items are in progress.


 Face brickwork to retaining walls are almost complete.

 Laying of vinyl floor covering and carpets are continuing.

 Furniture fitting is to complete.

 General external works continuing.


 Erection of canopies and glazing well advanced.


 Data installation progressing


The pavilion canopies (previously at Bewdley Road) have been installed at the new school.

The front canopy has been installed

Progress on the Primary outdoor areas

The assembly hall as seen from the dining area

Linoleum being laid around the atrium, level 1


Sixth form kitchenette

Key Stage 4 classroom