M & E finishing items are continuing.
Single ply roof covering flashings to complete.
Fitting of cedar fascia's, barge boards and window cheeks are complete, remedial works to do.
Decorations are continuing including snag items.
Gutter fixing is to complete.
Carpentry finishing items are continuing including snag items.
Laying of vinyl floor covering and carpets are continuing.
General external works continuing, including tarmacing.
Data installation progressing.
Generally all trades are progressing towards practical completion.