'Cell web' reinforcement is laid so the tarmac to teh minibus compound can be laid under the trees without damaging the roots. |
|
The top course of bricks is laid on the retaining wall. The bricklayers are coping well. |
|
Progress in the Hydrotherapy Pool |
|
Sheet flooring being laid in classrooms |
|
In stair 3, a test fitting of the ballustrade ahead of powder coating. |
Activity/Observation
M & E works are continuing.
Finishes to wall boarding and ceilings are continuing.
Acoustic separating floor system repairs and replacing of areas to complete.
Fitting of vertical slabs to the perimeter of the floor slab is continuing.
Single ply roof covering and flashings almost complete.
Fitting of cedar fascia's, barge boards and window cheeks are almost complete.
Decorations are continuing.
bulkheads, ceilings and suspended ceiling grids being erected.
Wall tiling is continuing, including tiling to hydro pool.
S.V.P.s and sink waste pipes being fitted.
Plumbing panels are continuing, basin and hinged rail fixings to address.
Works within Atrium is in progress.
Gutter fixing is to complete.
2nd fix Carpentry is continuing.
Storm water drainage connections from down pipe positions continuing.
Decking to enclosed external terraced areas to complete.
Face brickwork to retaining walls are progressing.
Laying of vinyl floor covering is progressing to various areas, including laying of liquid D.P.M.
Sports hall floor is in progress.
Furniture fitting is continuing.
General external works started.
Lift installation to both areas are continuing.
So what's next?
Continue external works, roof covering flashings, internal wall boarding, decorations and acoustic floor, 2nd fix Carpentry, M & E works, wall tiling, ceilings, furniture fitting, floor covering.