Friday, 29 August 2014

Early Years Hub - Week 14

The steelwork is now complete and timber infill well underway.

Cavity block work lift to around 1.2m to SE retaining walls RIW applied to rear
 Crane lift roofing liner panels
 Stanchion bases grouted
 1st and 2nd lift scaffold with access steps


Monday, 18 August 2014

Habberley Learning Village – Wyre Forest Special School - Week 58


Scaffolding being dismantled to the Campus Square elevation

Progress on the primary age wing


The sixth form terrace being waterproofed

Boilers and pipework installation in the main plant room


Ceilings being installed in the atrium (above a temporary scaffold platform)
 Activity/Observations Timber frame erection is almost complete.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc sheathing board is almost complete to external walls.
 Blown cavity insulation is continuing to walls and roof voids as areas become available.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are continuing.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is continuing.
 1st coat wall decorations are being carried out as areas become available.
 Metal framed bulkheads and ceilings being constructed.
 Soil and vent pipes and sink waste pipes being fitted and testing started.
 Plumbing panels are continuing.
 Works within Atrium is in progress.
 External scaffold is being dismantled.
Comments
So what's next?
 Continue scaffold erection, fitting of bitroc, window fitting and battening, vertical slabs to floor slab, air tightness membranes, roof coverings, internal wall boarding, mist coat decorations and acoustic floor, soil pipes etc.

Monday, 11 August 2014

Habberley Learning Campus– Wyre Forest Special School - Week 57

Progress around the main entrance and Sports Hall

Framework for the panelling concealing plumbing in toilet areas

One of the outdoor terraces


Ventilation ducts being installed in a first floor classroom
 Activity/Observations
 Timber frame erection is almost complete.
 Window and door fitting is continuing as areas are complete.
 Fitting of bitroc sheathing board is almost complete to external walls.
 Blown cavity insulation is continuing to walls and roof voids as areas become available.
 M & E works are in progress, including fitting of sprinkler system.
 Internal boarding to walls and ceilings are continuing.
 Acoustic separating floor system continuing (screed board floors to complete as areas become available).
 Fitting of vertical slabs to the perimeter of the floor slab is to be completed.
 Single ply roof covering is continuing and flashings to complete.
 Fitting of air tightness membranes are continuing.
 Fitting of cedar fascias and barge boards are continuing as areas become complete.
 Cape Cod cladding is continuing.
 Fitting of render boards and rendering is in progress.
 1st coat wall decorations are being carried out as areas become available.
 Metal framed bulkheads and ceilings being constructed.
 S.V.P.s and sink waste pipes being fitted and testing started.
 Plumbing panels started.