Progress on site: Science Block: Week 12
Activity/Observations
Excavation and concreting of foundations, including timber formwork to contain top of concrete pour is continuing.
Below slab foul drains continuing, ahead of localised concrete foundation pours and water test is in progress.
Drainage outside of footprint of building has started.
Shuttering at perimeter of floor slab has started.
Excavation and concreting of foundations, including timber formwork to contain top of concrete pour is continuing.
Below slab foul drains continuing, ahead of localised concrete foundation pours and water test is in progress.
Drainage outside of footprint of building has started.
Shuttering at perimeter of floor slab has started.
Progress on the Wyre Forest School - Week 12
Continue below ground drainage, tests carried out on each drain run when complete..
Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
Hydro pool construction is continuing.
Excavations to lift pit and trampoline pit are complete, damp proof membrane and reinforcement steelwork is in place.
Excavation for foul drainage at site boundary has started.
Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
Steel reinforcing fixing to retaining wall of south wing is in progress.
Concreting of floor slab to east wing is complete. Hydro pool construction is continuing.
Excavations to lift pit and trampoline pit are complete, damp proof membrane and reinforcement steelwork is in place.
Excavation for foul drainage at site boundary has started.
Overview of the busy site |
Friday, 4 October 2013
Progress on the Weekly Boarding Unit: Week 13
Substructure to slab
Strike perimeter formwork - ground floor slab complete
Erect perimeter scaffold ready to erect the timber frame
So what's next?
Erection of timber frame - the building will start to appear quickly once the prefabricated panels arrive.
Strike perimeter formwork - ground floor slab complete
Erect perimeter scaffold ready to erect the timber frame
So what's next?
Erection of timber frame - the building will start to appear quickly once the prefabricated panels arrive.