Continuing to lay below ground drainage.
Concreting of retaining wall / floor slab is continuing and preparation for floor slab pours are continuing.
Steel reinforcing fixing to retaining wall of south wing is in progress.
Shuttering, damp proof membrane. is in progress to east wing.
Excavation to hydrotherapy pool has been carried out and base is blinded with concrete.
Excavations to lift pit and trampoline pit are almost complete.
Science Block
Excavation and concreting of foundations, include timber formwork to contain top of pour is continuing approx 65% complete.
Below slab foul drains continuing to be laid, ahead of localised concrete foundation pours and water test is in progress.
Weekly Boarding Unit
Complete stone regarding/compaction + sand blind ready for the ground floor slab
Set up perimeter formwork
Lay floor insulation and damp proof membrane
Assemble steel fabric reinforcement ready to pour concrete